WeConnect 2.0

How do you standardize real-time operations and data capture for 500 field staff across 50 centers and 6 states — without the tool itself becoming another barrier to adoption?

PROBLEM STATEMENT
project summary

We Connect 2.0 is a custom-built application designed to replace fragmented, Excel-based field reporting with a single, standardized digital system. As Project Manager, I owned the project from content and information design through to execution — defining what each of 7 user personas needed to see and enter, while directing external design and development vendors, aligning leadership, and driving adoption among 500 end users across 6 states and 50 centers.

The challenge
  • Operations were run on inconsistent, center-specific spreadsheets with no shared standard, making oversight and data integrity difficult to maintain at scale. 

  • The end-user base was entirely non-technical field staff, with no prior experience using a structured digital tool. 

  • One persona (Center Head) carried disproportionately complex information needs — managing 6 other personas plus annual qualitative and quantitative target-setting. 

  • A compressed timeline meant the team had to weigh full bug resolution against the cost of delaying a much-needed operational shift.

strategy utilized
  • Phased, persona-by-persona rollout using agile-style sprints, allowing each of 7 personas to be independently designed, tested, and released rather than launching as one large system. 

  • Milestone-linked vendor payments, releasing funds only upon completion of each persona's design and development — keeping vendor delivery accountable to actual progress, not time elapsed. 

  • User-led UAT, testing each persona exclusively with the field staff who would use it day-to-day (e.g., Outreach Coordinators testing the Outreach Coordinator persona), on the premise that their operational fluency made them the most credible evaluators of usability. 

  • SLA-backed issue resolution, with a 2-working-day response and 2-working-day resolution target to manage post-launch bugs transparently.

Key decisions
  • Rejected the first design draft — a static, spreadsheet-style layout — and redirected the vendor to build an interactive interface, recognizing that replicating Excel would defeat the project's purpose. 

  • Re-planned the Center Head persona mid-execution after identifying that its scope was significantly more complex than initially scoped, adjusting design and development to match. 

  • Launched ahead of full bug resolution under timeline pressure, choosing to prioritize field momentum over a delayed, fully-polished release — supported by a structured live-support system to manage the trade-off.

noun-result-5751073 edited.png
results
  • 50 of 50 centers (100%) transitioned from Excel-based tracking to real-time digital reporting. 

  • 5 of 7 personas (71%) live and in active daily use by field teams. 

  • 500 end users onboarded onto a standardized operating system across 6 states. 

  • 2-working-day average issue response and resolution SLA maintained post-launch.

noun-lessons-learned-8348070 edited.png
Lesson learned

Launching before full technical readiness is a legitimate strategic choice — but only when backed by a fast, transparent support system. The real safeguard for adoption wasn't a perfect product at launch; it was a reliable, responsive process for resolving problems as real users encountered them.

noun-results-8092449 edited.png
outcome

We Connect 2.0 is now the operational backbone for field reporting across 6 states, with the remaining 2 personas and the deferred Youth profile positioned for phased rollout once current adoption stabilizes — extending the same standardization strategy across the organization's full operational base.